The Bayelsa State Government has confirmed that the 21-kilometre Nembe-Brass Road is nearing completion, with only 15 percent of work left.
The Commissioner for Works and Infrastructure, ESV Moses Teibowei, disclosed this on Friday, October 23, 2026, during an on-site inspection of the project alongside other government officials and journalists.
Teibowei said the project is on track for commissioning between March and April 2027, adding that equipment for the final stage is already on site.
“Only 15 percent of work is left on the Nembe-Brass Road. The company has set two weeks to launch the beams,” he said.

He noted that the contractor, Setraco, will launch the beams on the fifth and final bridge on the corridor within the next two weeks, and assured that quality control measures are being strictly enforced, with all materials tested at the Ministry’s laboratory in line with approved designs and the consultancy work by Prof. Beredugo.

Also speaking during the inspection, the Commissioner for Information, Orientation and Strategy, Mrs. Ebiuwou Koku-Obiyai, said work was still actively ongoing at the site, describing the road as a critical part of the prosperity administration’s infrastructural agenda.

On his part, the Area Manager of Setraco for Bayelsa State, Engr. Joajoa Cosme, said the company has completed sand-cement and the first layer of stone base up to kilometre 21 and finished the last box culvert.
He reaffirmed the March-April 2027 delivery timeline, stressing that the company has no funding issues with the state government and that the project remains a top priority of Governor Douye Diri.