President Bola Tinubu has directed that the Lagos-Calabar Coastal Highway be re-routed through the existing East-West road from Ondo into Edo State, the Minister of Works, Dave Umahi, has said.
According to TheCable, Umahi disclosed that the President gave the directive to avoid opening a fresh alignment along the corridor.
“Divert, do not do any new alignments. Pass the coastal highway through the existing East-West road,” the minister quoted Tinubu as saying.
He explained that the decision was also informed by persistent flooding along the East-West road, especially around the Ughelli axis in Delta State.
According to him, the road was constructed before the impact of climate change was adequately envisaged, adding that recent flooding had exposed its vulnerability.
Umahi said Delta State Governor, Sheriff Oborevwori, had raised concerns over the flooding, while the Federal Government is now planning to raise the road in several locations by about two metres above the existing level and anticipated flood levels.
The minister also defended the realignment of sections of the coastal highway in Ondo State, noting that the original route posed major engineering challenges.
“I am aware of petitions against me saying I diverted the Ondo section. I welcome that. But the important thing is whether you are doing the right thing or the wrong thing. We have no regret for decisions taken in Ondo,” he stated.
He said government had to take a difficult engineering decision to detour and redesign the alignment to avoid the difficult terrain, with filling of over 10 metres, about 30 feet, with sharp sand, which is nearing completion.
Umahi said the initial alignment passed through pits over 100 metres deep and areas without suitable sharp sand up to 300 metres depth, which would have escalated costs significantly.
He disclosed that the realignment affects Sections 4A and 4B, covering a total of 67 kilometres, with 27 kilometres in Ogun State and about 40 kilometres in Ondo State.
According to him, the corridor will terminate around the Ondo-Edo axis, while the 45-kilometre Benin bypass was designed to ease traffic congestion within Benin City. The combined Ondo-Edo corridor, including the bypass, is 104 kilometres.
Giving an update on the wider project, Umahi said Section One, a 47.47-kilometre stretch from Victoria Island in Lagos, has been completed and is ready for commissioning.
He said the dual pavement on Section Two, covering 55 kilometres and terminating at the Lagos-Ogun boundary, is expected to be completed next month.
The minister said flyovers, overpasses and underpasses along the section have been redesigned, particularly around the Dangote Refinery and Lekki Deep Seaport, to address traffic conflicts.
At the Calabar end, he said Sections 3A and 3B, covering 65 kilometres, have attained over 30 per cent completion.
He added that work is ongoing on Section Five, an 82-kilometre dual carriageway in Akwa Ibom State, as well as an 88-kilometre link from Calabar to Ebidi Beach to connect with the Trans-Saharan route.
Umahi further disclosed that route surveys and procurement are ongoing for a 129-kilometre dual carriageway from the Edo-Delta boundary to the Delta-Bayelsa boundary, with construction expected to begin in November.
He listed other Niger Delta projects including the 15-kilometre Eleme Junction to Onne road and the 9.7-kilometre Eket bypass.
According to him, contractors have also been mobilised for emergency repairs and reconstruction on the road linking Akwa Ibom to Calabar through Odukpani, noting that the contract previously handled by CCECC was reduced in scope due to funding constraints.