A licence procurement auditor, Dr. Isari Peregbe Samuel, has called on the people of Bayelsa State state as well as residents to be patient with the state government regarding the 60MW gas turbine project which is to supply Yenagoa and its environs with electricity.
The gas power plant was on Friday commissioned by President Bola Tinubu along other projects executed by the Douye Diri-led government, stirring expectations from citizens of its completion and functionality.
However, Isari in a statement on Saturday explained that the gas plant is yet to be operational after the installation and formal commissioning because it has been temporarily shut down to allow for testing and calibration which he said are “standard operating practice.”
He stressed that the temporary shutdown and delay in operation is not a sign of failure as wildly speculated.
According to him, “New turbines and their associated protection, control and grid-interfacing systems must be methodically checked, fine-tuned and certified before sustained commercial operation.
“The recent temporary shutdown is a procedural measure intended to guarantee safety, reliability and long-term performance—not a sign of failure.”
Isari further gave scenarios to explain why the temporary shutdown of the gas plant is normal and prudent.
He said, “Calibration and Break-In: New machines need controlled “break-in” operation and iterative tuning of control systems to protect components and optimize performance.
“Protection and Safety Checks: Safety interlocks and protection relays are thoroughly tested and, where necessary, adjusted to match local grid conditions.
“Grid Synchronization and Stability Tests: Engineers perform stepwise synchronization and load acceptance tests to ensure the turbine can operate stably with the wider network.
“Software and Control Integration: Control logic, SCADA interfaces and governor settings may require updates after initial commissioning runs.
“Manufacturer/OEM Verification: OEM teams often perform post-commissioning inspections and adjustments as part of warranty and reliability checks.”
Isari expressed support for Engr. Olice Kemenanabo, the Managing Director of the Bayelsa State Electricity Company, who is also the Technical Lead of the gas turbine project for what he described as his outstanding pedigree and consummate professionalism.
He described Kemenanabo as a man with mission and history, assuring that the Bayelsa electricity company MD remains committed to the optimal operationalization of the landmark gas turbine project.
He further reassured the people of the state that “the government and the technical teams of the Bayelsa State Electricity Company, supported by federal authorities and original equipment manufacturers, is doing everything necessary to bring the turbines to safe, stable and sustained operation as quickly as prudence allows.”
“This includes diagnostic testing, expert inspections, necessary adjustments, and coordinated grid readiness procedures,” he added.
Isari pleaded with the people of the state to be patient and maintained that “wild speculation and impatience will not accelerate a process that must be done carefully to protect lives, infrastructure and the long-term reliability of our power supply.”
He added that Bayelsans should also have faith in the “professionalism of Engr. Olice Kemenanabo and the dedication of the teams on the ground,” assuring that their expectation will not be dashed.